Drainage project could hit a snag
A $3.6 million project to improve drainage on Fountain Creek on the city’s west side and keep mine tailings from Gold Hill Mesa out of the water is in jeopardy, caught between competing visions for the creek.
Should the creek be as natural as possible, capable of supporting a healthy fish population, or should it be an urban drainage channel, funneling water downstream as quickly as possible?
City officials say if they can’t soon reach a consensus with the Colorado Division of Wildlife, which must issue a permit, the project may not happen.
“Our primary goals have to be flood control, reducing erosion and sedimentation, and water quality,” said Ken Sampley manager of the Colorado Springs Stormwater Enterprise, which is designing and paying for slightly less than half the project.
“We’ve never said we were building a trout stream,” Sampley said.But the DOW says the creek can be both.
“We still think it’s a viable fishery. It’s not like we’re trying to reach for the stars and make this into a gold-medal high-quality waterway,” said DOW senior aquatic biologist Doug Krieger. “What we want to do is give that habitat and the fish that live there every possibility for meeting as high a population as we can.”
The project is a collaboration among the Gold Hill Mesa developers, who are building houses on the tailings site and are obligated to keep runoff out of the creek; the Colorado Department of Transportation, which has long-term plans to widen U.S. 24 in the area; and the Stormwater Enterprise, which says erosion and water quality are problems in the stretch of creek, and the work is needed for flood control.
The project area is about 2,000 feet of the creek, to the west of the A-1 Mobile Village near Eighth Street.
The plan calls for lining 70 percent of the channel with rip-rap rocks grouted together to form a barrier – and keeping it wide, mostly straight and just a few inches deep, with channel-wide barriers across to control the grade of the creek.
The city has done similar projects on other stretches of the creek to the east and west, and DOW officials say fish have mostly disappeared from the sections. Despite the creek’s reputation as a low-flowing urban channel with water-quality issues, the agency says it has many fish.
In sections the city has improved, the water is too shallow and warm for fish to thrive, with too many barriers for fish to move, and the grouted rip-rap banks give insects on which they feed nowhere to breed.
The DOW must approve the project because a state agency, CDOT, is involved. It did not have to approve the other Fountain Creek projects.
“It’s difficult for us to be able to approve the permit under this fish stream protection act knowing we potentially will lose fish population,” DOW assistant regional manager Dave Lovell said. “We do understand the city’s desire for flood conveyance, and we’re trying to work with them and CDOT to try to achieve both goals.”
The local chapter of Trout Unlimited, a conservation group that works to restore waterways, last week issued a news release objecting to the project. The group had been working with the Stormwater Enterprise on its design.
The DOW and Trout Unlimited have asked the city to not grout the boulders in the rip-rap, keep the creek narrower, deeper with more curves and bends, and to remove from the plan some of the cross-creek barriers.
Sampley said he does not think the project could be secure without grouted rip-rap, because water could seep in and wash out the banks, allowing mine tailings to reach the water. He said Fountain Creek is not a natural environment now, having been moved over the years, so the city does not need to add more curves and oxbows.
“At some point we still have to make sure our design is going to be stable out there and prevent erosion,” Sampley said.
He said planners are working with the DOW on the design, but time is short. The city can’t advertise for bids until the DOW issues a permit, and if a contractor isn’t picked soon, they won’t be able to do spring planting of trees and willows needed for the project.
–
CONTACT THE WRITER: 476-1605 or srappold@gazette.com
An assortment of colored “Sweethearts” candy are held in bulk prior to packaging at the New England Confectionery Company in Revere, Mass, Wednesday Jan. 14, 2009. Photo by (AP Photo/Charles Krupa)